The latest update to the Valley Gardens work is available here.
The newsletter highlights:
• Complete road resurfacing
• Continue relandscaping of the gardens.
• Complete new paving and parking areas on the western side of the Old Steine.
• Install street furniture, including benches, cycle stands and bollards on the seafront.
• Lay new surface for cycle lane west of Steine Gardens and complete the new route between Marlborough Place and the seafront.
• Continue to lay resin bound gravel surface around the war memorial and gardens. The area currently underway around the war memorial will be finished once temperatures have cooled down.